Scored
Your Name
Journal Entry For
Module 9 - HVAC Systems
Created
Feb 28, 2025 9:54 PM
Last Edited
Mar 8, 2025 7:42 AM
Created by
V
Vlad ClimaFiles & media
Pinterest link
Text
https://pin.it/7idDoFsqa
My design strategy was to build a centralized HVAC system with a mechanical room on the ground floor and air handlers on the roof. The provided airflow is based on the highest load (cooling/heating/ventilating). I had some issues with some excessive cooling loads in some of the rooms and for now I managed to design enough ducts for the required airflow. This will be improved in the coming days. The ducts were placed in a way that they would sit directly underneath the structural beams. This for now leaves around 9 feet of headroom.
UPDATED (3/7/2025):
(Fixed the excessive airflow demands. Rerouted all the ducts in the building and fixed any errors. Connected the ducts to the Air Handling Units on the roof)