Fortunately, all of my bathrooms were aligned level to level so I only had to model one plumbing system and copy it up, then go back through and double check the connections.

My overall strategy was to try to make as few elements back to back as possible to limit the amount of custom piping that I would have to do as I found that it was something that I struggled with.

I also ran some of the sanitary pipes through the floor because it was difficult for me to make them all stay beneath the toilets.

Once the model was accurately leveled on model one I copied it up to the other floors, but also had to go back and copy monitor the floors and walls for the fixtures to be attatched to which took a few tries to figure out.