Student Exercise

Download Unit5_Lesson3_Exercise2_Start.zip:
Imperial or
MetricNavisworks Manage
- Use the project schedule to determine the date by which the material lift must be removed in order to avoid interfering with the installation of the building stair.
- Modify the schedule task linked to the materials lift so that it reflects the required installation and removal dates.
- Perform a time-based clash test between the Construction_Equipment and the Architectural_Shell models to confirm that a clash no longer exists between the materials lift and the stair. Be sure to link to the TimeLiner when you run this test in the Clash Detective tool.

Figure 5.3.4 - Adjusting the start and finish dates of the task associated with the temporary materials lift