Example - Piping Systems for Stacked Multi-User Restrooms



Note: The sanitary, vent, hot domestic water, and cold domestic water lines would connect to sources and terminals (for example, the sanitary sewer connection) at the Garage level.
You can download this model file here:
AI Prompts
Creating Plumbing Systems for Stacked Multi-User Restrooms
Prompt | Tool Options
š¢Ā = Autodesk Asst
šµĀ = Revit MCP
š£Ā = Python + Dynamo |
Add a piping systems to the multi-user restrooms in this multi-story office building.
Bathrooms:
⢠Run copper cold water supply lines to the lavatory sinks, toilets, and urinals.
⢠Run copper hot water supply lines to the lavatory sinks.
⢠Run sanitary drain lines and vent piping from all fixtures to a single drainage and vent stack in the bathroom riser space.
⢠Repeat this piping design on Levels L1 though L3.
Bathroom Riser & Piping Space:
⢠A bathroom riser and piping space is provided between the restrooms.
⢠Route the cold water, hot water, drainage, and vent lines through vertical risers that extend from the garage level (below L1) to the roof (level L4).
Garage Level Connections:
⢠Run horizontal trunk lines that connect the base of the vertical risers for each piping system at 20ā east of the riser locations at 10ā the Level Garage floor level.
As you work, send me a message after each step saying what you did and what you found. | š£ |
Claude Response
I'll connect to your open Revit model, inspect the restrooms, riser space, levels and available pipe types, then build the plumbing systems level by level, with an update after each step.
Now let me find the plumbing fixtures, rooms, and available pipe/system types.
Step 1 ā Model inventory done. Connected to 261105 Sample Stacked Offices Multi User RR.
- Levels: Garage (ā12'), L1 (0'), L2 (12'), L3 (24'), L4/roof (36').
- Fixtures: 36 total, 12 per level on L1āL3, identical stacked layout ā two back-to-back restrooms. East room (fixture face at Xā11.87'): 2 WCs, 2 urinals, 2 lavs. West room (Xā10.04'): 4 WCs, 2 lavs. All connectors face a ~1.8' wet wall between the rooms.
- No piping exists yet. System types available: Domestic Cold Water, Domestic Hot Water, Sanitary, Vent. Copper segments (K/L/M) exist but no copper pipe type is defined yet ā only "Default", "PVC - DWV", "Standard", "Chilled Water".
Next: locating the riser/piping space walls and checking what pipe types use which segments/fittings.
Read-only query timed out (possibly waiting for approval in Revit); retrying since it's harmless.
Step 2 ā Riser space & pipe types located.
- Riser/piping space: the chase between the 5" partitions at X=10.25' and X=11.67', running Yā39.3'ā59.3'. Clear width is only about 12"; fixture connectors sit on its outer wall faces. No shaft openings in the slabs (12" slabs at each floor), so risers will simply penetrate them.
- Pipe types: "Standard" uses Copper - K with generic welded fittings. "PVC - DWV" has proper sanitary tees/bends. I'll create two new types: Copper - Type L for CW/HW and a DWV type for sanitary/vent.
- Garage trunks: per your spec at elevation ā2' (10' above the Garage floor at ā12'), running 20' east of the risers.
Next: setting up the pipe types and testing how Revit handles tees on sloped drain lines before building the full layout.
Step 3 ā Fitting behavior tested (rolled back, nothing kept). Revit accepts sanitary tees and elbows on 1/8"/ft sloped drains with vertical branches, so drains can be properly sloped.
Layout I'm going with (chase is only ~12" clear, so every line has its own slot):
- Risers: Sanitary 4" at south end of chase; CW 2" and HW 1" beside it; Vent 3" at the north end of the chase.
- Water: CW header at 3'-7" AFF and HW header at 3'-2" AFF running along the chase; back-to-back fixtures share a cross-connection with a single tee up to the header.
- Sanitary: 4" horizontal branch under each floor slab (ceiling space below), sloped 1/8"/ft to the stack; WC/lav pairs drop into it; urinals tie in from the side.
- Vent: circuit vent off the upstream (north) end of each sanitary branch, tied into the vent stack at 5' AFF.
Next: creating the Copper Type L pipe type.
Pipe type created. Now building the full L1 layout (sanitary, vent branch, CW, HW) in one transaction ā it only commits if every pipe and fitting succeeds.
L1 committed with no errors. Quick verification of open pipe ends (should be exactly 4, the riser connection points) and fitting count:
Step 4 ā L1 restrooms piped and verified.
- 50 pipes + fittings committed; Revit auto-inserted reducers/transitions where branch sizes change (63 fittings total: sanitary tees, bends, generic tees/elbows, 2 crosses at the urinal rows).
- All 12 L1 fixtures fully connected ā every CW, HW and sanitary connector is attached.
- Sizes: WC 4" drains / 1" CW; urinals 2" drain / ¾" CW; lavs 1½" drain / ½" CW & HW; CW header 1½", HW header ¾"; sanitary branch 4" at 1/8"/ft; circuit vent 2".
- Exactly 4 open ends remain, all at the planned riser tie-in points (sanitary @ ā1.40', vent @ 5.0', CW @ 3.6', HW @ 3.2').
Next: repeating the identical design on L2 and L3.
Step 5 ā L2 and L3 restrooms piped. Same design repeated: 50 pipes per level, committed with zero fitting or connection errors. L1āL3 now each have a sanitary branch, circuit vent, CW and HW header waiting to tie into the risers.
Next: building the four vertical risers (Garage ā L4 roof), tying in all 12 branch connections, and running the 20' garage trunks.
Risers and trunks committed. Final verification ā open ends, fixture connectivity, systems, warnings, and a clash check between pipes of different systems:
The plumbing for the L1āL3 restrooms is built and checked. Nothing failed, so nothing was rolled back. The model is not saved yet.
What's in the model
- Fixtures: all 36 on L1āL3 are fully connected, with no open fixture connectors.
- Each level:
- Cold water goes to every WC, urinal and lavatory. Hot water goes to the lavatories only.
- Each level has a 4" sanitary branch sloped 1/8"/ft and a 2" circuit vent.
- Cold and hot water pipes are a new Copper - Type L pipe type. Sanitary and vent are the existing PVC - DWV type.
- Risers in the chase, Garage (ā2') to L4 (36'):
- Sanitary 4" and vent 3" each serve as the single stack for their system.
- Cold water 2" and hot water 1" risers.
- All 12 level branches tie into the risers with tees.
- Garage trunks: each riser elbows at ā2' (10' above the Garage floor) and runs 20' east.
- The sanitary trunk slopes 1/8"/ft, so it ends at ā2.21'. The other three trunks are level at ā2'.
- QA: 235 pipes and 214 fittings. No clashes between different systems and no piping warnings. The only open ends are the 4 riser tops at L4 and the 4 trunk ends.
Decisions you may want to review
- Drain branches under the slab: the chase is only about 12" clear. I ran each level's horizontal sanitary branch in the ceiling space below the slab, not inside the chase. On L1 that is the garage ceiling, between ā1.2' and ā1.4'.
- Urinal drains: these go straight down through the floor in front of the wall, then jog under the slab into the branch.
- Venting: I used one circuit vent per fixture group, taken off the far (north) end of each sanitary branch. There are no individual fixture vents or relief vents. Check this against your local code.
- Stack and riser tops: they stop at the L4 elevation, as you asked. The vent stack will need to extend through the roof, and the water riser tops will need caps.
- Trunk ends: all four are left open at 20' for connection to the building services.
- Sanitary trunk system name: Revit shows the trunk as a separate system ("Sanitary 3") even though it is physically connected to the stack. Reassigning it to the main sanitary system in the System Browser will fix that if you want one system.
Claude Spreadsheet Summary of Systems Created
I'll pull the pipe, fitting and fixture data from the model and build a summary spreadsheet.
No spreadsheet artifact type is available here, so I'll build an Excel file.
I'll have Revit aggregate the quantities so the data I carry into the workbook is compact and exact.
Data in hand. Building the workbook now.
Totals reconcile with the model (235 pipes, 214 fittings, 36 fixtures). Sending the workbook.
I've built the spreadsheet as an Excel file, Restroom_Plumbing_System_Summary.xlsx, from data pulled straight from the model. Its totals match the model: 235 pipes, 214 fittings and 36 fixtures.
The Summary tab gives these totals across the four systems:
System | Total length | Riser size |
Cold water | 164.9 ft | 2" |
Hot water | 78.8 ft | 1" |
Sanitary | 156.2 ft | 4" |
Vent | 70.7 ft | 3" |
All systems | 470.6 ft |
The Summary tab also breaks length down by level, counts the fixtures served (18 WCs, 6 urinals and 12 lavatories, all connected), and lists the model check results.
The other tabs are:
- Pipe Quantities: length and piece count by system, material, size and level.
- Fittings: counts by system, fitting family, size and level.
- Fixtures: every fixture's element ID, level, room and connection sizes.
- Risers & Trunks: riser locations, the elevation where each level ties in, and the trunk start and end points.
- Design Notes: the design criteria, assumptions and open items, such as extending the vent through the roof and capping the water riser tops.
Pipe lengths are measured along the pipe centerline and leave out the fittings, so expect to add an allowance when ordering material. All totals are formulas, so they update if you edit the detail tabs.