Which structural framing systems and materials are most commonly used in the United States for residences? For office buildings?
◦ What factors explain why those dominate?
◦ Why did you choose your system, and what did it cost you?
Answer: For houses and low and mid-rise apartments it is mostly light wood framing, studs and joists, and for mid-rise apartments it is usually wood over a concrete podium like mine. Offices are mostly steel frames with metal deck and concrete fill, and concrete frames show up more in taller residential towers and places where concrete is cheap. Wood dominates housing because it is cheap, every framer knows how to do it, the walls you need between apartments anyway can carry the load, and the code allows up to about five stories of it over a podium. Offices go steel because they want long open spans, fast erection and the flexibility to move walls around for different tenants, which wood cannot really give. I chose Type III wood over a 2 level concrete podium because my building is 7 floors of apartments over shops, so it fits the 5 over 2 limit without cutting any floors, and it matches the wood stud and concrete walls I already modeled in Module 4. What it cost me is flexibility. My spans are capped at about 25 to 30 ft, the wood floors have to land on walls that line up, and because the shops below want open space I needed a whole transfer level (a 14 in. slab plus 24x30 beams) at Level 3 to catch the wood walls that do not sit on columns.
You sized members by judgment rather than analysis.
◦ What did you base your first guess on?
◦ Why is it safer to guess large and shrink than to guess small and grow?
◦ At what point in a real project does the engineer take over from the guess?
Design teams link and share models rather than working in one file.
◦ What are the advantages of linking?
◦ What errors does linking make possible that a single model would not?
◦ Why is getting shared coordinates right at the start so much cheaper than fixing it later?
Not every clash is a problem.
◦ On what basis did you classify a clash as an issue versus not an issue?
◦ Who should have authority to close a clash on a real project?
Answer: My first check found a lot of clashes, but most of them were the same thing drawn twice. For example the concrete stair walls overlap the architectural stair walls, and the wood bearing walls overlap the architectural exterior walls, because both models show that wall on purpose. I called a clash an issue if fixing it changes the building or the drawings: a column or a concrete wall landing in a door, a window, a fixture or the stair run, a beam hanging below the ceiling, or a core that does not stack. I called it not an issue if it was a duplicate, a normal overlap like a wall running up into the slab above it, or a modeling tolerance that will not change anything in the field. On a real project I do not think the person who ran the clash should close it alone. The discipline that owns the element should agree it is fine (the architect for walls and openings, the engineer for anything structural), and the design lead or BIM coordinator closes it in the coordination meeting so there is a record of who decided.
Your beam depths just constrained next week's ductwork.
◦ Where in your building is the ceiling plenum now tightest?
◦ What would you give up to get it back?
◦ Should the structural engineer have consulted the mechanical engineer before setting spans?
Answer: The tightest place is Level 2, right under the Level 3 transfer level. The 14 in. slab plus 30 in. deep transfer beams take up 2'-6" of the 11 ft floor to floor, so under a beam there is about 8'-6" left, which is exactly my ceiling height, so there is basically no plenum there for ducts to cross the beam lines. The upper wood floors are a little better since the joists are only 16 in., but the ducts still have to run between joists or in a soffit. To get space back I would give up some of something: drop the ceiling to 8'-0" in the Level 2 corridor and baths, run the main ducts in the corridor parallel to the beams instead of across them, or raise the Level 2 floor to floor by 1 ft, which costs height and money. I do think the structural engineer should have talked to the mechanical engineer before setting spans, at least to agree where the main duct routes go. Changing a beam depth or adding a beam penetration later is way more expensive than picking a span that leaves a path for ducts now.