Which structural framing systems and materials are most commonly used in the United States for residences? For office buildings?
◦ What factors explain why those dominate? In the U.S., wood framing dominates residential buildings because it is cheap, fast to build, and easy to insulate, and in California specifically are used because it’s safer in case of a earthquake. Steel frames dominate office buildings because offices need wide, open floor plans without any interior walls blocking the space.
◦ Why did you choose your system, and what did it cost you? I chose a steel frame because my building has multiple floors in a U-shape and needed a strong, fast structure with an open first floor. What it cost me was higher material costs and extra coordination work to keep the structure from getting too heavy across the layout.
Design teams link and share models rather than working in one file.
◦ What are the advantages of linking? Each discipline (architects, structural engineers, etc) can work at the same time in their own clean file without accidentally deleting or messing up someone else's work.
◦ What errors does linking make possible that a single model would not? Models can end up floating in the wrong spot, rotated the wrong way, or at the wrong floor elevation if they aren't aligned properly, and teams can miss updates if someone forgets to upadte the latest link.
◦ Why is getting shared coordinates right at the start so much cheaper than fixing it later? If the coordinates are wrong from the very start, every beam, column, and pipe gets built in the wrong place. Fixing it later means moving thousands of elements across multiple files, which breaks tags, sheets, and dimensions.
Not every clash is a problem.
◦ On what basis did you classify a clash as an issue versus not an issue? I marked a clash as a real issue when it compromised structural integrity, looked strange on the exterior, or blocked a usable room (like my outside beam sticking out past the walls, a stray wall going through the floor, and a ceiling crashing into upper framing). I marked clashes as not an issue when they were just harmless modeling overlaps, like floor slabs touching core walls.
◦ Who should have authority to close a clash on a real project? Only the BIM Manager alongside the responsible discipline lead (like the Lead Structural Engineer or Lead Architect) should have authority to close a clash after verifying the fix in the model.