Sanitary drainage must slope; supply piping does not.
◦ How did that single rule change your plan?
It made me put the sanitary riser right behind the fixtures, in the wall between units 205 and 206. Water pipes can go anywhere, but the drains need to fall, so every foot of horizontal drain costs height. Even with the riser that close, the toilet and lavatory drains still ended up below the floor structure, because each one needed its own tee on the riser.
◦ Where would you locate restrooms differently if you started over?
I would put the bathrooms of neighboring units back to back, next to a real shaft near the core, and stack them the same on every floor. Then one riser could serve two bathrooms and the drains would stay short.
Building science: efficient lighting and controls.
◦ Which controls strategy would most reduce your lighting energy, and why?
◦ How do your Week 3 window-to-wall ratio and your Week 4 glazing and shading choices show up in this week’s lighting load?
You modelled a representative slice rather than the whole building.
◦ What did the slice teach you that would have been buried in a full model?
It let me focus on the small details: the tub being longer than the room, the lavatory facing the wrong way, and the fittings needing more space than I thought. In a full model I would probably just copy the bathroom everywhere and never notice those problems.
◦ What might a slice hide that only a full model would reveal?
The bigger picture: total pipe sizes when all units connect, how all the risers go through the ground floor and the lobby, and clashes with ducts and beams in other parts of the building. One stack looks fine alone, but many stacks together can be a different story.
Panels, risers and mechanical rooms all compete for the same square footage.
◦ How much of your floor area is now given over to systems?
◦ Is that a failure of planning or a normal cost of a working building?
You now have five models from five notional disciplines.
◦ Who is responsible when two of them disagree?
It depends on the clash, but usually the one who can move more easily fixes it, and the structure normally wins. For example, a pipe moves around a beam, not the other way around. Someone also needs to own the coordination, like a BIM coordinator or the architect, so the issue doesn't just sit there.
◦ What would go wrong if all five were one file instead?
Everyone would work in the same file, so it gets slow and heavy, and one mistake can break someone else's work. It would also be harder to know who changed what, and you lose the clear ownership that each discipline has over its own model.