Module 9 - Points to Ponder

Link to Student
Submitted For
Module 9 - Points to Ponder
đź’ˇ
Please share your comments on 3 of the following 5 questions.

How was design coordination done before digital models?

◦  What did teams do instead, and what did it cost in rework?

Prior to digital models, design coordination had to be done using 2D models. Methods included overlay drafting, use of composite drawings, and reliance on experience to determine potential clashes across discipline models. This cost teams significantly in terms of rework, since 2D models are much more costly and time-consuming to fix than 3D models.

◦  Is there anything the older methods caught that a clash report does not?

Not all the clashes listed in a clash report may be an actual issue for the design; similarly, since the clash report primarily looks at geometrical clashes for the modelled elements, it doesn’t necessarily confirm that the design intent, sizing, and routing of systems meets building codes in the region. In addition to running a clash report, it’s important to have senior engineers/architects/construction workers to review the plans as well, to ensure the constructability of a project.

At what point should design coordination start?

◦  Is it ever too early?

It’s good to start design coordination when decisions are made in the different discipline models that will affect other disciplines (i.e. concept and schematic design phase). Ideally, design coordination should start once there are multiple discipline models for a project. However, depending on the level of detail of the model, clashes should be classified accordingly (for example, if the models are in the concept and schematic phase, project teams should worry about larger clashes between the architectural system and major structural columns or start considering the size of the plenum space for the electrical and mechanical equipment). It is never too early to start design coordination, but this does not mean you need to resolve all the clashes before moving onto the next step of the design process.

◦  What would have been different if you had run this in Week 4?

If I had run this clash analysis in Week 4, it would have likely been easier to fix identified clashes, but the modelled clashes would not have been fully representative of the entire design, since only the architectural model was complete by this week.

◦  What is the cost of finding a conflict now versus during construction?

By finding a conflict now and resolving it is much less costly than having to fix a clash during the construction process. Resolving a 3D building model clash is much easier, since everything is still hosted digitally and nothing has been build yet. On the other hand, identifying a clash during the construction phase and resolving it can result in a chain of costs (labour, equipment, material costs, as well as time delays), making it much more costly to resolve.

One discipline generated more issues than the others.

◦  Which, and why do you think that is?

My architectural model had the most clashes (closely followed by the structural model). One reason for this was because the architectural model was the first model built - at this stage of the design process, there were a lot of assumptions made for the initial design which all went into the architectural model and later tricked into the structural and MEP models. Specifically, the architectural and structural models clashed significantly, especially due to the placement of structural beams and columns around the elevators and mechanical shaft error (found during an earlier module). In hindsight, I should have left more room between these rooms to accommodate for structural supports, however it was not considered as it didn’t show up in the design decisions that needed to be made for the architectural model.

◦  Is that a property of the discipline or of how you modelled it?

This is likely a property of how I modelled my building. In practice, typically the MEP systems would have more clashes, since they have to routed through the ceiling plenum space after architectural and structural features have been decided. In addition, the complexity of MEP systems (includes numerous elements) and sometimes inflexible design (i.e. duct runs) also tend to significantly increase the potential clashes between system equipment, such as ducts, pipes, fittings, compared to the architectural model.