Module 7 Template

Link to Student
Submitted For
Module 7 - Comfort Zone

Working links to all three models in Forma Data Management and your Forma Board

Please paste your working links to all three models and your Board here…

PDF sheet set at E1 size, 30 by 42 inches

Please paste your PDF sheet set here…

Load summary table: floor total and by zone

Please paste your load summary table here…

Alternatives comparison: your representative unit and your alternative unit, compared by numbers, with your conclusion

Metric
Representative unit (107)
Alternative unit (105)
Total duct length
about 35'-3 3/8" (34'-0 3/8" supply + 1'-3 1/16" return)
about 44'-6" (39'-9 3/4" supply + 4'-8 7/32" return)
Largest duct size after sizing
11×11
11×11
Highest branch velocity
595 FPM
595 FPM
Clear height at the unit entry, from the section
7'-6" to ceiling; 9'-2 1/8" to the floor above
7'-6" to ceiling; 9'-2 1/8" to the floor above
Clear height in the corridor, from the section
7'-6" to ceiling; 9'-2 1/8" to the floor above
7'-6" to ceiling; 9'-2 1/8" to the floor above
Ducts crossing the rated corridor wall
0 - fan coil, supply and return are all inside the unit
1 - the supply
Refrigerant line set length
about 37 ft routed, estimated
about 41 ft routed, estimated
Maintenance access
only by entering the unit
from the corridor ceiling, without entering the unit
Conclusion
Keeping the fan coil inside 107 gives about 9 ft less duct, no corridor-wall crossings and a shorter line set, but service means entering the dwelling.
Putting 105’s fan coil in the corridor makes service easier, but costs more duct, at least one rated-wall penetration and a longer line set.
Choice
I’d select the in-unit fan coil (107): shorter duct and line set and no rated-wall penetrations, at the cost of in-unit service access.

Design memo of 300 to 500 words: your strategy and why, what the loads told you about your envelope, where your structure got in the way, and what you left unresolved

Please paste your design memo here…