Module 8

Link to Student
Submitted For
Module 8 - Wired and Plumbed
💡

Please enter the following info in the fields above:

  • Link to Student (type the first few letter of your name, then select yourself in the list of linked records)
💡

What to Submit

  1. Working links to all five models in Forma Data Management (architectural, structural, mechanical, plumbing and electrical) and your Individual Forma Board.
  2. PDF sheet set at E1 size, 30 by 42 inches, four sheets: plumbing plan, riser section showing the sanitary fall, power plan, lighting plan.
  3. Your illumination spot check result.
  4. Design memo of 300 to 500 words: where the sanitary riser went and why, what gravity forced you to change, whether your daylighting reduced your lighting load, and what you left unresolved.

Working links to all five models in Forma Data Management (architectural, structural, mechanical, plumbing and electrical) and your Individual Forma Board

Board: https://app.autodeskforma.com/board/up_b1ucsl7wxr/board_326d5eb9-f755-4517-a2de-ee069cf131a6

Arch: https://acc.autodesk.com/docs/files/projects/523e14cd-482e-410a-be5e-ea207a875e34?folderUrn=urn%3Aadsk.wipprod%3Afs.folder%3Aco.jTkhENDvQuysqYRJMv1brQ&entityId=urn%3Aadsk.wipprod%3Adm.lineage%3ALquNRdEeQv-s5EUQJCv-Cg&viewModel=detail&moduleId=folders

Struct: https://acc.autodesk.com/docs/files/projects/523e14cd-482e-410a-be5e-ea207a875e34?folderUrn=urn%3Aadsk.wipprod%3Afs.folder%3Aco.jTkhENDvQuysqYRJMv1brQ&entityId=urn%3Aadsk.wipprod%3Adm.lineage%3AZHAKfW-tSGaJEbanaTOuRA&viewModel=detail&moduleId=folders

Mech: https://acc.autodesk.com/docs/files/projects/523e14cd-482e-410a-be5e-ea207a875e34?folderUrn=urn%3Aadsk.wipprod%3Afs.folder%3Aco.jTkhENDvQuysqYRJMv1brQ&entityId=urn%3Aadsk.wipprod%3Adm.lineage%3Ado-l5SJzQeqTUN-iqoKVKQ&viewModel=detail&moduleId=folders

Plumbing: https://acc.autodesk.com/docs/files/projects/523e14cd-482e-410a-be5e-ea207a875e34?folderUrn=urn%3Aadsk.wipprod%3Afs.folder%3Aco.jTkhENDvQuysqYRJMv1brQ&entityId=urn%3Aadsk.wipprod%3Adm.lineage%3AMDvuZ2MbT46qDTPQBHr7eQ&viewModel=detail&moduleId=folders

Elect: https://acc.autodesk.com/docs/files/projects/523e14cd-482e-410a-be5e-ea207a875e34?folderUrn=urn%3Aadsk.wipprod%3Afs.folder%3Aco.jTkhENDvQuysqYRJMv1brQ&entityId=urn%3Aadsk.wipprod%3Adm.lineage%3Ad5pUD_bKSUGWfibTrXfcCQ&viewModel=detail&moduleId=folders

PDF sheet set at E1 size, 30 by 42 inches, four sheets: plumbing plan, riser section showing the sanitary fall, power plan, lighting plan

Power plan and lighting plan are on the same sheet, therefore it is 3 sheets.

Grantm11_module8.pdf338.3 KiB

Your illumination spot check result

image

Design memo of 300 to 500 words: where the sanitary riser went and why, what gravity forced you to change, whether your daylighting reduced your lighting load, and what you left unresolved

The 4” sanitary stack was placed on the wall behind the water closet (toilet) because the lavatory (vanity sink) is next to it on the same wall and the kitchen sink, though not included in this module, is along the same wall nearby. There are two short horizontal branches and one longer. The 3” branch from the toilet which is right at the stack and 1 ¼” branch from the lavatory a few feet away, but the 2” branch from the bathtub is a bit longer at about 8’. The toilet was the main driver for the location decision because it requires the largest drain, with the least flexibility. It is important to note that since we were only instructed to model three stories, the stack stops just shy of the ground floor and will require further modelling to drain from the building. This stack will not be used for the commercial ground floor if the current design is applied since the restrooms on the ground floor are not close by. Daylight does not reduce my lighting load because the lighting load is determined based on having all lights on. Lights must still work at night, so the full load is necessary regardless. It is also worthy to note that there are no daylight controls placed in this current model. The load is relatively low because the fixtures are efficient and there are lights that will need to be added to meet the illuminance standards in the dining room, living room, bedroom and bathroom. Daylighting can reduce energy use over time but would not reduce the connected load that sizes the panel. The first iteration of lighting for the kitchen did not meet the target illuminance, so it was reconsidered. Following a second iteration, the kitchen now reaches 294 lx, which falls within the 215-320 lx target range. The same iteration process will be required for all other rooms in unit 410 since none of the initial lighting plans provide the required illuminance. The wiring to the building is left incomplete and only the one unit on the fourth floor was modelled for this module’s electrical system. Based on the modelled load alone, the panel is adequate. It is a 100A, 120/208 V, three phase panel that can carry about 36kVA. It carries a connected load of about 4886 VA, roughly 14% of its capacity. The analytical model estimates about 1395 VA for the unit, using 1 W/SF for lighting and 1.3W/SF for power. The panel load is much higher because it counts design capacity, which would be 180 VA per receptacle and 1500 VA for the fan coil instead of relying on averages. Currently the major appliances are not yet circuited, so that is why its usage is so low. With the in-unit washer and dryer, the 100A panel would not have enough breaker spaces, so it should be upsized. A 125 A panel with 24 spaces would be more fitting for this unit.

I realized too late that I was supposed to model the plumbing where I have the air duct already placed. I did not hear it mentioned in the video, but I should have known better. I do not have time (or energy) to fix it this week, but if it is a critical step, please let me know and I can redo it at a later time. I understand the importance of modelling those in the same space on a conceptual level, I just know modelling, even with Claude, will take me another 8 hours.